Filters
Question type

Study Flashcards

Traditionally, much of aggregate planning is focused within an enterprise and may not always be seen as a part of supply chain management.

A) True
B) False

Correct Answer

verifed

verified

A highly effective tool for a company to use when it tries to maximize profits while being subjected to a series of constraints is


A) aggregate programming.
B) distribution programming.
C) production programming.
D) linear programming.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Demand is forecast for the next five months as 200, 300, 500, 300, 200. The production planner decides to adopt a chase strategy, so over the next five months they should produce


A) 200, 300, 500, 300, 200.
B) 500, 400, 300, 200, 100.
C) 100, 200, 300, 400, 500.
D) 300, 300, 300, 300, 300.

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

Companies should work with downstream partners to produce forecasts and with upstream partners to determine constraints when doing aggregate planning.

A) True
B) False

Correct Answer

verifed

verified

True

A poor aggregate plan can result in


A) appropriate inventory levels.
B) efficient use of capacity.
C) better sales and lost profits.
D) lost sales and lost profits.

E) A) and B)
F) B) and C)

Correct Answer

verifed

verified

Safety capacity is defined as capacity used to satisfy demand that is lower than forecasted.

A) True
B) False

Correct Answer

verifed

verified

Most strategies that an aggregate planner actually uses are in combination, and are referred to as hybrid strategies.

A) True
B) False

Correct Answer

verifed

verified

The fundamental trade-offs available to an aggregate planner are between


A) capability, inventory, and backlog costs.
B) capability, inventory, and sales costs.
C) capacity, inventory, and backlog costs.
D) capacity, inventory, and sales costs.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Much of aggregate planning has traditionally been focused


A) on short-term production scheduling.
B) on customer relationship management.
C) within an enterprise.
D) beyond enterprise boundaries.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

The planning horizon is


A) the time period over which the aggregate plan is to produce a solution.
B) the duration of each time period in the aggregate plan.
C) the length of time required to produce the aggregate plan.
D) the solution to the aggregate plan.

E) A) and C)
F) B) and D)

Correct Answer

verifed

verified

The operational parameter concerned with the number of units completed per unit time (such as per week or per month) is


A) production rate.
B) workforce.
C) overtime.
D) backlog.

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

As capacity utilization increases,


A) it becomes less important to perform aggregate planning.
B) it becomes more important to perform aggregate planning.
C) it does not affect the importance of performing aggregate planning.
D) it lessens the importance of aggregate planning.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Scenario 8.2 - Willow A company faces the aggregate planning problem shown in the table below. Cost of regular production is $8 per unit, the cost of producing the same unit on overtime is $15, the cost of subcontracting is $12 per unit, and the cost of carrying a unit in inventory from one month to the next is $6.  January  February  March  April  May  Forecast 4008001200700300 Beginning Inventory 100 Regular Time  Qvertime  Subcontracting  Ending Inventory \begin{array}{|l|c|c|c|c|c|}\hline & \text { January } & \text { February } & \text { March } & \text { April } & \text { May } \\\hline \text { Forecast } & 400 & 800 & 1200 & 700 & 300 \\\hline \text { Beginning Inventory } & 100 & & & & \\\hline \text { Regular Time } & & & & & \\\hline \text { Qvertime } & & & & & \\\hline \text { Subcontracting } & & & & & \\\hline \text { Ending Inventory } & & & & & \\\hline\end{array} The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five month window. The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week. By policy, management wants to avoid stockouts. -How many units are produced using overtime in the optimal aggregate plan developed to address Scenario 8.2?


A) 360
B) 200
C) 400
D) 280

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

D

The aggregate plan needs to


A) be a final product because changes are disruptive to the supply chain.
B) be considered fixed because forecasts are usually accurate.
C) have some flexibility built into it because forecasts are always wrong.
D) have some flexibility built into it because forecasts are usually right.

E) B) and D)
F) None of the above

Correct Answer

verifed

verified

The operational parameter concerned with the planned inventory carried over the various periods in the planning horizon is


A) production rate.
B) overtime.
C) backlog.
D) inventory on hand.

E) B) and D)
F) All of the above

Correct Answer

verifed

verified

Scenario 8.2 - Willow A company faces the aggregate planning problem shown in the table below. Cost of regular production is $8 per unit, the cost of producing the same unit on overtime is $15, the cost of subcontracting is $12 per unit, and the cost of carrying a unit in inventory from one month to the next is $6.  January  February  March  April  May  Forecast 4008001200700300 Beginning Inventory 100 Regular Time  Qvertime  Subcontracting  Ending Inventory \begin{array}{|l|c|c|c|c|c|}\hline & \text { January } & \text { February } & \text { March } & \text { April } & \text { May } \\\hline \text { Forecast } & 400 & 800 & 1200 & 700 & 300 \\\hline \text { Beginning Inventory } & 100 & & & & \\\hline \text { Regular Time } & & & & & \\\hline \text { Qvertime } & & & & & \\\hline \text { Subcontracting } & & & & & \\\hline \text { Ending Inventory } & & & & & \\\hline\end{array} The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five month window. The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week. By policy, management wants to avoid stockouts. -How many months does the regular time output exceed plant capacity in the optimal solution to Scenario 8.2?


A) 0
B) 1
C) 2
D) 3

E) All of the above
F) None of the above

Correct Answer

verifed

verified

Aggregate planning should consider information from


A) only the enterprise as its breadth of scope.
B) downstream partners to produce forecasts.
C) upstream partners to determine constraints.
D) all of the above

E) None of the above
F) A) and B)

Correct Answer

verifed

verified

D

To create an aggregate plan, a company must specify the planning horizon for the plan and the duration of each period within the planning horizon.

A) True
B) False

Correct Answer

verifed

verified

Aggregate planning is concerned with determining


A) the production level, sales level, and capacity for each period.
B) the demand level, inventory level, and capacity for each period.
C) the production level, inventory level, and capacity for each period.
D) the production level, staffing level, and capacity for each period.

E) B) and C)
F) All of the above

Correct Answer

verifed

verified

Explain the basic strategies that an aggregate planner has available to balance the various costs and meet demand.

Correct Answer

verifed

verified

There are essentially three distinct agg...

View Answer

Showing 1 - 20 of 76

Related Exams

Show Answer