Project management software is important because it will manage the project for the project manager.

A) True
B) False

Correct Answer

verifed

verified

Gene is trying to order the concrete needed to continue his project.However, the supplier will not be able to deliver it until next week.This is an example of what kind of resource constraint?


A) Working capital
B) People
C) Equipment
D) Information
E) Materials

F) A) and B)
G) B) and E)

Correct Answer

verifed

verified

All of the following are types of resource constraints EXCEPT


A) Materials.
B) People.
C) Equipment.
D) Information.
E) Human.

F) B) and C)
G) None of the above

Correct Answer

verifed

verified

In order that the new product is on the shelf for the Christmas buying season, the development of the new product would be classified as a(n)________ -constrained project.

Correct Answer

verifed

verified

time
Explanation: A time-constrained pro...

View Answer

A shortage of programmers to write software is an example of a(n)________ type of resource constraint.

Correct Answer

verifed

verified

people
Explanation: This is the most obv...

View Answer

Why is it necessary to have a time-phased budget baseline?


A) It allows proper resource allocation.
B) It shows how much work was accomplished for the money spent.
C) It reduces schedule slippage when scheduling multiproject resources.
D) It is not necessary to have a time-phased budget baseline.
E) It reduces fluctuations in cash flow during the project.

F) A) and D)
G) None of the above

Correct Answer

verifed

verified

When considering the sequence and timing of activities, which of the following is NOT one of the types of project network constraints?


A) Physical
B) Technical
C) Resource
D) Time
E) All of these are types of constraints that could impact structure of the project network.

F) C) and E)
G) D) and E)

Correct Answer

verifed

verified

Project managers should always assign the best people to the most difficult tasks.

A) True
B) False

Correct Answer

verifed

verified

When classifying projects, ________ constrained means that project duration is fixed and resources are flexible.

Correct Answer

verifed

verified

time
Explanation: In schedulin...

View Answer

Startup and shutdown costs are major considerations when using the ________________ scheduling technique.

Correct Answer

verifed

verified

splitting or multitasking
Expl...

View Answer

When looking at the critical path for a delayed project and the project manager sees that adding resources will reduce or remove the delay, the project manager knows that the project is


A) Over Allocated.
B) Time-Constrained.
C) Institutionally Challenged.
D) Ahead of schedule.

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

A lack of readily available engineers is a technical constraint.

A) True
B) False

Correct Answer

verifed

verified

Why is it critical to form a time-phased budget?

Correct Answer

verifed

verified

Without a time-phased budget it is diffi...

View Answer

Which of the following is NOT one of the more common problems associated with scheduling multiproject resources?


A) Overall schedule slippage
B) Inefficient resource utilization
C) Decline in project quality
D) Resource bottlenecks
E) Delays in one project causing delays in other projects

F) A) and B)
G) None of the above

Correct Answer

verifed

verified

Which of the following is NOT a potential consequence of failing to identify limited resources before project implementation?


A) Activity delays
B) Project delays
C) Difficulty in taking quick corrective action
D) Increase costs
E) Scope creep

F) A) and E)
G) B) and E)

Correct Answer

verifed

verified

Resource dependency takes priority over the technological dependency but does not violate ___________ dependencies.

Correct Answer

verifed

verified

technical
Explanation: Resource dependen...

View Answer

Resource leveling or smoothing is only used on projects which are resource constrained.

A) True
B) False

Correct Answer

verifed

verified

Why should project managers be cautious about using the splitting scheduling technique?

Correct Answer

verifed

verified

The splitting technique is where an acti...

View Answer

Susan is to conduct environmental testing but the chamber cannot hold all the equipment that she wants to test.This is an example of a constraint that could impact the sequence and timing of activities in a project network.What type of constraint is it?


A) Physical
B) Technical
C) Resource
D) Scheduling
E) Time

F) A) and E)
G) D) and E)

Correct Answer

verifed

verified

Many companies are ________ project work to contractors and consultants as a means of dealing with the peaks and valleys of resource allocation among projects.

Correct Answer

verifed

verified

outsourcing
Explanation: Many companies ...

View Answer