Filters
Question type

Study Flashcards

The goal of aggregate planning is to satisfy demand in a way that minimizes profit.

A) True
B) False

Correct Answer

verifed

verified

Demand is forecast for the next five months as 200,300,500,300,200.The production planner decides to adopt a level strategy,so over the next five months they should produce


A) 200,300,500,300,200.
B) 500,400,300,200,100.
C) 100,200,300,400,500.
D) 300,300,300,300,300.

E) C) and D)
F) None of the above

Correct Answer

verifed

verified

As inputs into the aggregate plan change,managers do not need to make changes to the aggregate plan.

A) True
B) False

Correct Answer

verifed

verified

Linear programming finds the solution for an aggregate plan that creates the highest profit while satisfying the constraints that a company faces.

A) True
B) False

Correct Answer

verifed

verified

As capacity utilization increases,it becomes less important to perform aggregate planning.

A) True
B) False

Correct Answer

verifed

verified

The aggregate planning problem is concerned with determining the production level,inventory level,and capacity level (internal and outsourced)for each period that maximizes the firm's profit over the planning horizon.

A) True
B) False

Correct Answer

verifed

verified

The length of the planning horizon in aggregate planning is usually between


A) one and three months.
B) three and eighteen months.
C) one and three years.
D) three and five years.

E) B) and C)
F) A) and B)

Correct Answer

verifed

verified

Aggregate planning solves problems involving


A) aggregate decisions and stock keeping unit (SKU) level decisions.
B) aggregate decisions or stock keeping unit (SKU) level decisions.
C) aggregate decisions rather than stock keeping unit (SKU) level decisions.
D) stock keeping unit (SKU) level decisions rather than aggregate decisions.

E) B) and D)
F) All of the above

Correct Answer

verifed

verified

The aggregate plan should be communicated to


A) only the local firm.
B) only downstream partners.
C) only upstream partners.
D) all supply chain partners who will be affected by it.

E) B) and D)
F) A) and C)

Correct Answer

verifed

verified

Scenario 8.3 - Mousetraps A company faces the aggregate planning problem shown in the table below.Cost of regular production is $15 per unit,the cost of producing the same unit on overtime is $22.50,the cost of subcontracting is $27 per unit,and the cost of carrying a unit in inventory from one month to the next is $10.  July  August  September  October  November  Forecast 800650450550900 Beginning Inventory 140 Regular Time  Overtime  Subcontracting  Ending Inventory \begin{array} { | l | c | c | c | c | c | } \hline & \text { July } & \text { August } & \text { September } & \text { October } & \text { November } \\\hline \text { Forecast } & 800 & 650 & 450 & 550 & 900 \\\hline \text { Beginning Inventory } & 140 & & & & \\\hline \text { Regular Time } & & & & & \\\hline \text { Overtime } & & & & & \\\hline \text { Subcontracting } & & & & & \\\hline \text { Ending Inventory } & & & & & \\\hline\end{array} The labor contract at the plant prohibits both overtime and subcontracting output to exceed 250 units in any five-month window.The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week.By policy,management wants to avoid stockouts. -Which month has a positive ending inventory for the optimal aggregate plan for Scenario 8.3?


A) August
B) September
C) October
D) November

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

An aggregate planning horizon is usually between three and five years.

A) True
B) False

Correct Answer

verifed

verified

Scenario 8.2 - Willow A company faces the aggregate planning problem shown in the table below.Cost of regular production is $8 per unit,the cost of producing the same unit on overtime is $15,the cost of subcontracting is $12 per unit,and the cost of carrying a unit in inventory from one month to the next is $6.  January  February  March  April  May  Forecast 4008001200700300 Beginning Inventory 100 Regular Time  Overtime  Subcontracting  Ending Inventory \begin{array} { | l | c | c | c | c | c | } \hline & \text { January } & \text { February } & \text { March } & \text { April } & \text { May } \\\hline \text { Forecast } & 400 & 800 & 1200 & 700 & 300 \\\hline \text { Beginning Inventory } & 100 & & & & \\\hline \text { Regular Time } & & & & & \\\hline \text { Overtime } & & & & & \\\hline \text { Subcontracting } & & & & & \\\hline \text { Ending Inventory } & & & & & \\\hline\end{array} The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five-month window.The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week.By policy,management wants to avoid stockouts. -How many units are produced using overtime in the optimal aggregate plan developed to address Scenario 8.2?


A) 360
B) 200
C) 400
D) 280

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Discuss the primary objective and operational parameters of aggregate planning.

Correct Answer

verifed

verified

The goal of aggregate planning is to sat...

View Answer

When formulating aggregate plans,


A) forecast errors have no impact.
B) forecast errors must be taken into account.
C) forecast accuracy is assumed.
D) forecast accuracy is not a factor.

E) None of the above
F) B) and C)

Correct Answer

verifed

verified

Scenario 8.3 - Mousetraps A company faces the aggregate planning problem shown in the table below.Cost of regular production is $15 per unit,the cost of producing the same unit on overtime is $22.50,the cost of subcontracting is $27 per unit,and the cost of carrying a unit in inventory from one month to the next is $10.  July  August  September  October  November  Forecast 800650450550900 Beginning Inventory 140 Regular Time  Overtime  Subcontracting  Ending Inventory \begin{array} { | l | c | c | c | c | c | } \hline & \text { July } & \text { August } & \text { September } & \text { October } & \text { November } \\\hline \text { Forecast } & 800 & 650 & 450 & 550 & 900 \\\hline \text { Beginning Inventory } & 140 & & & & \\\hline \text { Regular Time } & & & & & \\\hline \text { Overtime } & & & & & \\\hline \text { Subcontracting } & & & & & \\\hline \text { Ending Inventory } & & & & & \\\hline\end{array} The labor contract at the plant prohibits both overtime and subcontracting output to exceed 250 units in any five-month window.The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week.By policy,management wants to avoid stockouts. -How many units are produced using overtime in the optimal aggregate plan developed to address Scenario 8.3?


A) 250
B) 200
C) 100
D) 180

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

Scenario 8.1 - Gang Aft Agley Gang Aft Agley,a manufacturing company,faces the aggregate planning problem shown in the table below.Cost of regular production is $5 per unit,the cost of producing the same unit on overtime is $7.50,the cost of subcontracting is $9 per unit,and the cost of carrying a unit in inventory from one month to the next is $2.  January  February  March  April  May  Forecast 5007501200650300 Beginning Inventory 100 Regular Time  Overtime  Subcontracting  Ending Inventory \begin{array} { | l | c | c | c | c | c | } \hline & \text { January } & \text { February } & \text { March } & \text { April } & \text { May } \\\hline \text { Forecast } & 500 & 750 & 1200 & 650 & 300 \\\hline \text { Beginning Inventory } & 100 & & & & \\\hline \text { Regular Time } & & & & & \\\hline \text { Overtime } & & & & & \\\hline \text { Subcontracting } & & & & & \\\hline \text { Ending Inventory } & & & & & \\\hline\end{array} The labor contract at the plant prohibits both overtime and subcontracting output to exceed 300 units in any five month window.The plant capacity is 600 units per month produced using two shifts,regardless of the number of days in a month.By policy,management wants to avoid stockouts. -What is the optimal total cost of the aggregate plan developed to address Scenario 8.1?


A) $16,700
B) $18,950
C) $18,450
D) $16,250

E) A) and C)
F) None of the above

Correct Answer

verifed

verified

Scenario 8.2 - Willow A company faces the aggregate planning problem shown in the table below.Cost of regular production is $8 per unit,the cost of producing the same unit on overtime is $15,the cost of subcontracting is $12 per unit,and the cost of carrying a unit in inventory from one month to the next is $6.  January  February  March  April  May  Forecast 4008001200700300 Beginning Inventory 100 Regular Time  Overtime  Subcontracting  Ending Inventory \begin{array} { | l | c | c | c | c | c | } \hline & \text { January } & \text { February } & \text { March } & \text { April } & \text { May } \\\hline \text { Forecast } & 400 & 800 & 1200 & 700 & 300 \\\hline \text { Beginning Inventory } & 100 & & & & \\\hline \text { Regular Time } & & & & & \\\hline \text { Overtime } & & & & & \\\hline \text { Subcontracting } & & & & & \\\hline \text { Ending Inventory } & & & & & \\\hline\end{array} The labor contract at the plant prohibits both overtime and subcontracting output to exceed 400 units in any five-month window.The plant capacity is 20 units per day produced using two shifts and the plant runs seven days a week.By policy,management wants to avoid stockouts. -What is the optimal total cost of the aggregate plan developed to address Scenario 8.2?


A) $27,200
B) $20,960
C) $31,400
D) $26,600

E) B) and C)
F) A) and D)

Correct Answer

verifed

verified

The goal of aggregate planning is to


A) maximize the amount of inventory.
B) satisfy customers in a way that minimizes production.
C) satisfy demand in a way that maximizes profit.
D) maximize the amount of product shipped.

E) All of the above
F) C) and D)

Correct Answer

verifed

verified

The process by which a company determines levels of capacity, production, subcontracting, inventory, stockouts, and even pricing over a specified time horizon is


A) aggregate planning.
B) detail planning.
C) inventory planning.
D) sales planning.

E) A) and B)
F) A) and C)

Correct Answer

verifed

verified

A highly effective tool for a company to use when it tries to maximize profits while being subjected to a series of constraints is


A) aggregate programming.
B) distribution programming.
C) production programming.
D) linear programming.

E) A) and D)
F) B) and C)

Correct Answer

verifed

verified

Showing 21 - 40 of 85

Related Exams

Show Answer